N. |
Title |
WP |
Diss. level |
1.2 |
GEN – Requirement No. 5 |
WP1 |
Confidential |
D12.1 |
Press conference |
WP12 |
Public |
D12.2 |
Project website |
WP12 |
Public |
D11.1 |
Project documentation for upgrade and extension of laboratory and office space for the Centre. |
WP11 |
Public |
D11.2 |
Detailed specifications of planned research infrastructure. |
WP11 |
Public |
D3.1 |
Documents attesting formal establishment of the Centre and approval of its organisational structure by the scientific board and academic senate of TNUAD |
WP3 |
Public |
D3.2 |
Lists of SB, IAB, and IB members |
WP3 |
Public |
D3.3 |
Minutes from the kick-off SB, IAB and IB meetings |
WP3 |
Confidential |
D2.6 |
Reports on cumulative expenditures 2017 |
WP2 |
Confidential |
D1.1 |
EPQ – Requirement No. 2 |
WP1 |
Confidential |
D12.3 |
Annual press conference 1 |
WP12 |
Public |
D2.1 |
Implementation report 1 |
WP2 |
Confidential |
D6.1 |
Set of rules implemented by all partners for management of advanced research facilities |
WP6 |
Confidential |
D7.2 |
Maria Curie Research Training Network project prepared for submission |
WP7 |
Confidential |
D10.1 |
Report on research activities in the previous reporting period, including list of publications 1 |
WP10 |
Public |
D11.3 |
Report on the upgrade and extension of laboratory and office space for the Centre. |
WP11 |
Confidential |
D4.1 |
Report on the progress of hiring and contracting activities 1 |
WP4 |
Confidential |
D5.1 |
Report on the progress of hiring and contracting activities and creation of the CAU |
WP5 |
Confidential |
D7.1 |
Plan of training stays and visits |
WP7 |
Confidential |
D9.1 |
Abbreviated summary of reports from training activities in the previous reporting period 1 |
WP9 |
Confidential |
D2.7 |
Reports on cumulative expenditures 2018 |
WP2 |
Confidential |
D12.4 |
Annual press conference 2 |
WP12 |
Public |
D2.2 |
Implementation report 2 |
WP2 |
Confidential |
D2.8 |
Reports on cumulative expenditures 2019 |
WP2 |
Confidential |
D10.2 |
Report on research activities in the previous reporting period, including list of publications 2 |
WP10 |
Public |
D12.5 |
Annual press conference 3 |
WP12 |
Public |
D4.2 |
Report on the progress of hiring and contracting activities 2 |
WP4 |
Confidential |
D8.1 |
New study plans and curricula for the FunGlass Centre |
WP8 |
Public |
D9.2 |
Abbreviated summary of reports from training activities in the previous reporting period 2 |
WP9 |
Confidential |
D2.3 |
Implementation report 3 |
WP2 |
Confidential |
D2.9 |
Reports on cumulative expenditures 2020 |
WP2 |
Confidential |
D11.4 |
Updated system of management system for advanced research facilities |
WP11 |
Confidential |
D12.6 |
Annual press conference 4 |
WP12 |
Public |
D10.3 |
Report on research activities in the previous reporting period, including list of publications 3 |
WP10 |
Public |
D4.3 |
Report on the progress of hiring and contracting activities 3 |
WP4 |
Confidential |
D9.3 |
Abbreviated summary of reports from training activities in the previous reporting period 3 |
WP9 |
Confidential |
D2.10 |
Reports on cumulative expenditures 2021 |
WP2 |
Confidential |
D8.2 |
Agreement signed by the statutory representatives of TnUAD and partner institutions on joint/double diplomas |
WP8 |
Public |
D10.4 |
Joint H2020 research grant application prepared for submission 1 |
WP10 |
Confidential |
D12.7 |
Annual press conference 5 |
WP12 |
Public |
D2.4 |
Implementation report 4 |
WP2 |
Confidential |
D2.11 |
Reports on cumulative expenditures 2022 |
WP2 |
Confidential |
D10.5 |
Joint H2020 research grant application prepared for submission 2 |
WP10 |
Confidential |
D10.6 |
Report on research activities in the previous reporting period, including list of publications 4 |
WP10 |
Public |
D12.8 |
Annual press conference 6 |
WP12 |
Public |
D4.4 |
Report on the progress of hiring and contracting activities 4 |
WP4 |
Confidential |
D9.4 |
Abbreviated summary of reports from training activities in the previous reporting period 4 |
WP9 |
Confidential |
D10.7 |
Joint H2020 research grant application prepared for submission 3 |
WP10 |
Confidential |
D2.12 |
Reports on cumulative expenditures 2023 |
WP2 |
Confidential |
D10.8 |
Report on research activities in the previous reporting period, including list of publications 5 |
WP10 |
Public |
D10.9 |
Joint H2020 research grant application prepared for submission 4 |
WP10 |
Confidential |
D12.9 |
Annual press conference 7 |
WP12 |
Public |
D2.5 |
Final Implementation report |
WP2 |
Confidential |
D4.5 |
Final report on the progress of hiring and contracting activities |
WP4 |
Confidential |
D9.5 |
Abbreviated summary of reports from training activities in the previous reporting period 5 |
WP9 |
Confidential |